Deliverable | Deliverable title | Work Package | Original due date |
---|---|---|---|
D1.1 | Project Management Internal Handbook | 1 | 31 March 2014 |
D1.2 | Project Report Interim | 1 | 31 July 2015 |
D1.3 | Project Report | 1 | 31 March 2017 |
D1.4 | Final Project Report | 1 | 31 July 2017 |
D2.1 | Detailed Mobility Plan | 2 | 30 September 2014 |
D2.2 | Secondment Reports | 2 | 30 September 2015 |
D2.3 | Recruitment contracts and key staff integration report | 2 | 31 March 2017 |
D3.1 | Procurement of the tender | 3 | 30 September 2014 |
D3.2 | Contracts for acquisition | 3 | 31 March 2016 |
D3.3 | Equipment Installation Report | 3 | 30 September 2016 |
D4.1 | Coaching and Networking Training Program | 4 | 31 May 2014 |
D4.2 | Coaching and Networking Events Calendar | 4 | 31 August 2014 |
D4.3 | Report on Proposal Preparation Training Session | 4 | 31 December 2014 |
D4.4 | Report on Strategic Positioning Training | 4 | 28 February 2015 |
D4.5 | Report on legal and financial training | 4 | 30 April 2015 |
D4.6 | Report on meetings with Technology/ Platform representatives | 4 | 29 February 2016 |
D4.7 | Report on follow-up with Key Research Organisations | 4 | 31 January 2016 |
D4.8 | Report on Networking Activities | 4 | 30 November 2016 |
D4.9 | Report on participation in events | 4 | 30 November 2016 |
D5.1 | First coaching report | 5 | 30 November 2014 |
D5.2 | Second coaching report | 5 | 31 January 2015 |
D5.3 | Strategy for connections with and support to industry and economic development | 5 | 31 March 2015 |
D5.4 | UHI Innovation Policy | 5 | 31 May 2015 |
D5.5 | Report on Innovation Support Office | 5 | 31 March 2017 |
D5.6 | Plan for use and dissemination of foreground IP | 5 | 31 July 2017 |
D6.1 | Dissemination and communication plan | 6 | 30 April 2014 |
D6.2 | Website online publication | 6 | 31 July 2014 |
D6.3 | Production of dissemination material | 6 | 30 September 2014 |
D6.4 | Individual Dissemination Report Work | 6 | 31 March 2017 |
D6.5 | Proceedings of UHI Research Day in Brussels | 6 | 31 March 2016 |
D6.6 | Proceedings from the UHI MERIKA Industry Dissemination Event | 6 | 31 January 2017 |
D6.7 | Report overall on dissemination activities | 6 | 31 March 2017 |
D7.1 | Ex-post Evaluation Report | 7 | 30 June 2017 |
D7.2 | Final assessment of Project Outcome | 7 | 31 July 2017 |